Isbell Construction Project Plan

A32 UNIT - The Villas at Old Greenwood



Start Date: Thu 8/25/05
Finish Date: Tue 7/18/06

NameDurationStart DateFinish DatePredecessors
A 32229 daysWed 8/31/05Mon 7/17/06 
EXCAVATION28 daysWed 8/31/05Fri 10/7/05 
Clear & Grub2 daysWed 8/31/05Thu 9/1/05 
Build Pad3 daysFri 9/2/05Tue 9/6/053
Dig Footings1 dayWed 9/7/05Wed 9/7/054
Stub Utilities1 dayThu 9/8/05Thu 9/8/055
Backfill2 daysFri 9/23/05Mon 9/26/0516
Dig Piers & Slab Prep1 dayWed 9/28/05Wed 9/28/0517
Install Utilities2 daysTue 10/4/05Wed 10/5/05 
Driveway & Final Grade2 daysThu 10/6/05Fri 10/7/059
FOUNDATION20 daysFri 9/2/05Thu 9/29/05 
Layout Footings1 dayFri 9/2/05Fri 9/2/053
Form Foundation5 daysFri 9/9/05Thu 9/15/056
Set Hardware1 dayFri 9/16/05Fri 9/16/0513
Pour Foundation1 dayTue 9/20/05Tue 9/20/05140
Strip Forms2 daysWed 9/21/05Thu 9/22/0515
Layout Piers1 dayTue 9/27/05Tue 9/27/057
Pour Slabs and Piers1 dayThu 9/29/05Thu 9/29/058
FRAMING159 daysThu 11/17/05Tue 6/27/06 
Subfloor5 daysMon 11/7/05Fri 11/11/05 
Sheet Floor2 daysMon 11/28/05Tue 11/29/0551
First Floor Walls8 daysWed 2/15/06Fri 2/24/0621
Second Floor7 daysMon 2/27/06Tue 3/7/0622
Second Floor Walls18 daysWed 3/8/06Fri 3/31/0623
Roof Framing15 daysMon 4/3/06Fri 4/21/0624
Sheet Roof5 daysMon 4/24/06Fri 4/28/0625
Interior Frame & Shear5 daysMon 5/1/06Fri 5/5/0626
Framing Pick-up5 daysMon 5/8/06Fri 5/12/0627
Tyvek4 daysMon 4/24/06Thu 4/27/0625
Windows5 daysFri 4/28/06Thu 5/4/0629
Exterior Doors2 daysFri 5/5/06Mon 5/8/0630
Siding25 daysTue 5/9/06Mon 6/12/0631
Decks6 daysTue 6/13/06Tue 6/20/0632
Exterior Pick-up5 daysWed 6/21/06Tue 6/27/0633
EXTERIOR STAIN5 daysWed 6/28/06Tue 7/4/0634
A UNIT176 daysMon 11/14/05Mon 7/17/06 
PLUMBING162 daysMon 11/14/05Tue 6/27/06 
Under Floor3 daysMon 11/14/05Wed 11/16/0520
Top Out5 daysMon 5/1/06Fri 5/5/0626
Finish4 daysThu 6/22/06Tue 6/27/0661
HVAC158 daysThu 11/17/05Mon 6/26/06 
Under Floor2 daysThu 11/17/05Fri 11/18/0538
Top Out3 daysMon 5/8/06Wed 5/10/0639
Set Equipment1 dayMon 6/12/06Mon 6/12/0663
Finish1 dayMon 6/26/06Mon 6/26/0675
ELECTRICAL83 daysMon 2/27/06Wed 6/21/06 
Set Panel1 dayMon 2/27/06Mon 2/27/0622
Rough In6 daysThu 5/11/06Thu 5/18/0643
Finish4 daysFri 6/16/06Wed 6/21/0667
INSULATION128 daysFri 11/25/05Tue 5/23/06 
Under Floor1 dayFri 11/25/05Fri 11/25/05141
Walls & Roof2 daysMon 5/22/06Tue 5/23/06146
DRYWALL12 daysMon 5/22/06Tue 6/6/06 
Stock1 dayMon 5/22/06Mon 5/22/06146
Hang4 daysTue 5/23/06Fri 5/26/0654
Tape & Texture6 daysTue 5/30/06Tue 6/6/06152
TILE18 daysMon 5/29/06Wed 6/21/06 
Shower Pans1 dayMon 5/29/06Mon 5/29/0655
Showers5 daysMon 6/12/06Fri 6/16/0663
Slabs4 daysWed 6/14/06Mon 6/19/0670
Floors3 daysMon 6/19/06Wed 6/21/0659
PAINTING14 daysWed 6/7/06Mon 6/26/06 
Interior Walls3 daysWed 6/7/06Fri 6/9/0656
Putty & Caulk3 daysThu 6/29/06Mon 7/3/0673
Final Touch Up1 dayMon 6/26/06Mon 6/26/0675
FINISH CARPENTRY13 daysMon 6/12/06Wed 6/28/06 
Ceilings2 daysWed 6/14/06Thu 6/15/0670
Doors & Casing2 daysFri 6/16/06Mon 6/19/0667
Window Trim2 daysTue 6/20/06Wed 6/21/0668
Cabinets2 daysMon 6/12/06Tue 6/13/0663
Stair Rails 1 dayThu 6/22/06Thu 6/22/0669
Baseboard2 daysMon 6/26/06Tue 6/27/0674
Closets & Pick Up1 dayWed 6/28/06Wed 6/28/0672
HARDWOOD FLOORS2 daysThu 6/22/06Fri 6/23/0669
CARPET1 dayFri 6/23/06Fri 6/23/0688
SHOWER ENCLOSURES2 daysThu 6/22/06Fri 6/23/0661
ROOFING20 daysTue 5/2/06Mon 5/29/06 
Dry In1 dayTue 5/2/06Tue 5/2/06144
Flashings2 daysMon 5/15/06Tue 5/16/0628
Roof18 daysThu 5/4/06Mon 5/29/06143
MASONRY30 daysWed 5/17/06Tue 6/27/06 
Interior4 daysMon 6/12/06Thu 6/15/0663
Exterior30 daysWed 5/17/06Tue 6/27/0679
OVERHEAD DOORS1 dayWed 6/28/06Wed 6/28/0634
APPLIANCES16 daysThu 6/1/06Thu 6/22/06 
Fireplace1 dayWed 6/7/06Wed 6/7/0656
Hood1 dayWed 6/14/06Wed 6/14/0670
Appliances1 dayThu 6/22/06Thu 6/22/0649
B UNIT173 daysThu 11/17/05Mon 7/17/06 
PLUMBING169 daysThu 11/17/05Tue 7/11/06 
Underfloor3 daysThu 11/17/05Mon 11/21/0538
Top Out5 daysMon 5/8/06Fri 5/12/0639
Finish4 daysThu 7/6/06Tue 7/11/06127
HVAC163 daysTue 11/22/05Thu 7/6/06 
Under Floor2 daysTue 11/22/05Wed 11/23/0591
Top Out3 daysMon 5/15/06Wed 5/17/0692
Set Equipment1 dayThu 6/22/06Thu 6/22/06116
Finish1 dayThu 7/6/06Thu 7/6/06127
ELECTRICAL97 daysMon 2/27/06Tue 7/11/06 
Set Panel1 dayMon 2/27/06Mon 2/27/0622
Rough In6 daysThu 5/18/06Thu 5/25/0696
Finish4 daysThu 7/6/06Tue 7/11/06127
INSULATION133 daysFri 11/25/05Tue 5/30/06 
Under Floor1 dayFri 11/25/05Fri 11/25/05141
Walls & Roof2 daysMon 5/29/06Tue 5/30/06147
DRYWALL12 daysThu 6/1/06Fri 6/16/06 
Stock1 dayThu 6/1/06Thu 6/1/06150
Hang4 daysFri 6/2/06Wed 6/7/06107
Tape & Texture6 daysFri 6/9/06Fri 6/16/06153
TILE18 daysThu 6/8/06Mon 7/3/06 
Shower Pans1 dayThu 6/8/06Thu 6/8/06108
Showers5 daysThu 6/22/06Wed 6/28/06116
Slabs4 daysMon 6/26/06Thu 6/29/06123
Floors3 daysThu 6/29/06Mon 7/3/06112
PAINTING20 daysMon 6/19/06Fri 7/14/06 
Interior Walls3 daysMon 6/19/06Wed 6/21/06109
Putty & Caulk3 daysThu 7/6/06Mon 7/10/06127
Final Touch Up1 dayFri 7/14/06Fri 7/14/06128
FINISH CARPENTRY13 daysThu 6/22/06Mon 7/10/06 
Ceilings2 daysMon 6/26/06Tue 6/27/06123
Doors & Casing2 daysWed 6/28/06Thu 6/29/06120
Window Trim2 daysFri 6/30/06Mon 7/3/06121
Cabinets2 daysThu 6/22/06Fri 6/23/06116
Stair Rails1 dayTue 7/4/06Tue 7/4/06122
Baseboard2 daysThu 7/6/06Fri 7/7/06127
Closets & Pick Up1 dayMon 7/10/06Mon 7/10/06125
HARDWOOD FLOORS2 daysTue 7/4/06Wed 7/5/06122
CARPET1 dayThu 7/13/06Thu 7/13/06133
SHOWER ENCLOSURES2 daysTue 7/4/06Wed 7/5/06114
APPLIANCES18 daysMon 6/19/06Wed 7/12/06 
Fireplaces1 dayMon 6/19/06Mon 6/19/06109
Hood1 dayMon 6/26/06Mon 6/26/06123
Appliances1 dayWed 7/12/06Wed 7/12/06102
FINAL CLEAN2 daysMon 7/17/06Tue 7/18/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysMon 10/10/05Tue 10/11/0510
Final Lift1 dayMon 5/1/06Mon 5/1/06 
LANDSCAPING5 daysMon 5/1/06Fri 5/5/06 
INSPECTIONS214 daysWed 9/21/05Mon 7/17/06 
Foundation1 dayMon 9/19/05Mon 9/19/0514
Underfloor1 dayThu 11/24/05Thu 11/24/0595
Framing & Shear1 dayMon 5/15/06Mon 5/15/0628
Ice Dam1 dayWed 5/3/06Wed 5/3/0678
Roof Nailing1 dayMon 5/1/06Mon 5/1/0626
ROUGH6 daysFri 5/19/06Fri 5/26/06 
A Unit1 dayFri 5/19/06Fri 5/19/0648
B Unit1 dayFri 5/26/06Fri 5/26/06101
INSULATION6 daysWed 5/24/06Wed 5/31/06 
A Unit1 dayWed 5/24/06Wed 5/24/0652
B Unit1 dayWed 5/31/06Wed 5/31/06105
DRYWALL9 daysMon 5/29/06Thu 6/8/06 
A Unit1 dayMon 5/29/06Mon 5/29/0655
B Unit1 dayThu 6/8/06Thu 6/8/06108
SHOWER PAN1 dayFri 6/9/06Fri 6/9/06111
FINAL 1 dayMon 7/17/06Mon 7/17/06118