Isbell Construction Project Plan

A33 UNIT - The Villas at Old Greenwood



Start Date: Thu 8/25/05
Finish Date: Mon 6/26/06

NameDurationStart DateFinish DatePredecessors
A 33218 daysWed 8/24/05Fri 6/23/06 
EXCAVATION31 daysWed 8/24/05Wed 10/5/05 
Clear & Grub2 daysWed 8/24/05Thu 8/25/05 
Build Pad3 daysFri 8/26/05Tue 8/30/053
Dig Footings1 dayWed 8/31/05Wed 8/31/054
Stub Utilities1 dayThu 9/1/05Thu 9/1/055
Backfill2 daysFri 9/16/05Mon 9/19/0516
Dig Piers & Slab Prep1 dayWed 9/21/05Wed 9/21/0517
Install Utilities2 daysFri 9/30/05Mon 10/3/05 
Driveway & Final Grade2 daysTue 10/4/05Wed 10/5/059
FOUNDATION17 daysWed 8/31/05Thu 9/22/05 
Layout Footings1 dayWed 8/31/05Wed 8/31/054
Form Foundation5 daysFri 9/2/05Thu 9/8/056
Set Hardware1 dayFri 9/9/05Fri 9/9/0513
Pour Foundation1 dayTue 9/13/05Tue 9/13/05140
Strip Forms2 daysWed 9/14/05Thu 9/15/0515
Layout Piers1 dayTue 9/20/05Tue 9/20/057
Pour Slabs and Piers1 dayThu 9/22/05Thu 9/22/058
FRAMING157 daysMon 10/31/05Tue 6/6/06 
Subfloor5 daysMon 10/31/05Fri 11/4/05 
Sheet Floor2 daysMon 11/21/05Tue 11/22/0551
First Floor Walls8 daysWed 1/25/06Fri 2/3/06 
Second Floor7 daysMon 2/6/06Tue 2/14/0622
Second Floor Walls18 daysWed 2/15/06Fri 3/10/0623
Roof Framing15 daysMon 3/13/06Fri 3/31/0624
Sheet Roof5 daysMon 4/3/06Fri 4/7/0625
Interior Frame & Shear5 daysMon 4/10/06Fri 4/14/0626
Framing Pick-up5 daysMon 4/17/06Fri 4/21/0627
Tyvek4 daysMon 4/3/06Thu 4/6/0625
Windows5 daysFri 4/7/06Thu 4/13/0629
Exterior Doors2 daysFri 4/14/06Mon 4/17/0630
Siding25 daysTue 4/18/06Mon 5/22/0631
Decks6 daysTue 5/23/06Tue 5/30/0632
Exterior Pick-up5 daysWed 5/31/06Tue 6/6/0633
EXTERIOR STAIN5 daysWed 6/7/06Tue 6/13/0634
A UNIT157 daysThu 11/17/05Fri 6/23/06 
PLUMBING152 daysMon 11/7/05Tue 6/6/06 
Under Floor3 daysMon 11/7/05Wed 11/9/0520
Top Out5 daysMon 4/10/06Fri 4/14/0626
Finish4 daysThu 6/1/06Tue 6/6/0661
HVAC148 daysThu 11/10/05Mon 6/5/06 
Under Floor2 daysThu 11/10/05Fri 11/11/0538
Top Out3 daysMon 4/17/06Wed 4/19/0639
Set Equipment1 dayMon 5/22/06Mon 5/22/0663
Finish1 dayMon 6/5/06Mon 6/5/0675
ELECTRICAL83 daysMon 2/6/06Wed 5/31/06 
Set Panel1 dayMon 2/6/06Mon 2/6/0622
Rough In6 daysThu 4/20/06Thu 4/27/0643
Finish4 daysFri 5/26/06Wed 5/31/0667
INSULATION118 daysFri 11/18/05Tue 5/2/06 
Under Floor1 dayFri 11/18/05Fri 11/18/05141
Walls & Roof2 daysMon 5/1/06Tue 5/2/06146
DRYWALL12 daysMon 5/1/06Tue 5/16/06 
Stock1 dayMon 5/1/06Mon 5/1/06146
Hang4 daysTue 5/2/06Fri 5/5/0654
Tape & Texture6 daysTue 5/9/06Tue 5/16/06152
TILE18 daysMon 5/8/06Wed 5/31/06 
Shower Pans1 dayMon 5/8/06Mon 5/8/0655
Showers5 daysMon 5/22/06Fri 5/26/0663
Slabs4 daysWed 5/24/06Mon 5/29/0670
Floors3 daysMon 5/29/06Wed 5/31/0659
PAINTING14 daysWed 5/17/06Mon 6/5/06 
Interior Walls3 daysWed 5/17/06Fri 5/19/0656
Putty & Caulk3 daysThu 6/8/06Mon 6/12/0673
Final Touch Up1 dayMon 6/5/06Mon 6/5/0675
FINISH CARPENTRY13 daysMon 5/22/06Wed 6/7/06 
Ceilings2 daysWed 5/24/06Thu 5/25/0670
Doors & Casing2 daysFri 5/26/06Mon 5/29/0667
Window Trim2 daysTue 5/30/06Wed 5/31/0668
Cabinets2 daysMon 5/22/06Tue 5/23/0663
Stair Rails 1 dayThu 6/1/06Thu 6/1/0669
Baseboard2 daysMon 6/5/06Tue 6/6/0674
Closets & Pick Up1 dayWed 6/7/06Wed 6/7/0672
HARDWOOD FLOORS2 daysThu 6/1/06Fri 6/2/0669
CARPET1 dayFri 6/2/06Fri 6/2/0688
SHOWER ENCLOSURES2 daysThu 6/1/06Fri 6/2/0661
ROOFING20 daysTue 4/11/06Mon 5/8/06 
Dry In1 dayTue 4/11/06Tue 4/11/06144
Flashings2 daysMon 4/24/06Tue 4/25/0628
Roof18 daysThu 4/13/06Mon 5/8/06143
MASONRY30 daysWed 4/26/06Tue 6/6/06 
Interior4 daysMon 5/22/06Thu 5/25/0663
Exterior30 daysWed 4/26/06Tue 6/6/0679
OVERHEAD DOORS1 dayWed 6/7/06Wed 6/7/0634
APPLIANCES16 daysWed 5/17/06Wed 6/7/06 
Fireplace1 dayWed 5/17/06Wed 5/17/0656
Hood1 dayWed 5/24/06Wed 5/24/0670
Appliances1 dayThu 6/1/06Thu 6/1/0649
B UNIT162 daysThu 11/10/05Fri 6/23/06 
PLUMBING158 daysThu 11/10/05Mon 6/19/06 
Underfloor3 daysThu 11/10/05Mon 11/14/0538
Top Out5 daysMon 4/17/06Fri 4/21/0639
Finish4 daysWed 6/14/06Mon 6/19/06127
HVAC144 daysFri 11/25/05Wed 6/14/06 
Under Floor2 daysTue 11/15/05Wed 11/16/0591
Top Out2 daysMon 4/24/06Tue 4/25/0692
Set Equipment1 dayWed 5/31/06Wed 5/31/06116
Finish1 dayWed 6/14/06Wed 6/14/06127
ELECTRICAL96 daysMon 2/6/06Mon 6/19/06 
Set Panel1 dayMon 2/6/06Mon 2/6/0622
Rough In6 daysWed 4/26/06Wed 5/3/0696
Finish4 daysWed 6/14/06Mon 6/19/06127
INSULATION122 daysFri 11/18/05Mon 5/8/06 
Under Floor1 dayFri 11/18/05Fri 11/18/05141
Walls & Roof2 daysFri 5/5/06Mon 5/8/06147
DRYWALL12 daysWed 5/10/06Thu 5/25/06 
Stock1 dayWed 5/10/06Wed 5/10/06150
Hang4 daysThu 5/11/06Tue 5/16/06107
Tape & Texture6 daysThu 5/18/06Thu 5/25/06153
TILE18 daysWed 5/17/06Fri 6/9/06 
Shower Pans1 dayWed 5/17/06Wed 5/17/06108
Showers5 daysWed 5/31/06Tue 6/6/06116
Slabs4 daysFri 6/2/06Wed 6/7/06123
Floors3 daysWed 6/7/06Fri 6/9/06112
PAINTING20 daysFri 5/26/06Thu 6/22/06 
Interior Walls3 daysFri 5/26/06Tue 5/30/06109
Putty & Caulk3 daysMon 6/19/06Wed 6/21/06126
Final Touch Up1 dayThu 6/22/06Thu 6/22/06128
FINISH CARPENTRY13 daysWed 5/31/06Fri 6/16/06 
Ceilings2 daysFri 6/2/06Mon 6/5/06123
Doors & Casing2 daysTue 6/6/06Wed 6/7/06120
Window Trim2 daysThu 6/8/06Fri 6/9/06121
Cabinets2 daysWed 5/31/06Thu 6/1/06116
Stair Rails1 dayMon 6/12/06Mon 6/12/06122
Baseboard2 daysWed 6/14/06Thu 6/15/06127
Closets & Pick Up1 dayFri 6/16/06Fri 6/16/06125
HARDWOOD FLOORS2 daysMon 6/12/06Tue 6/13/06122
CARPET1 dayWed 6/21/06Wed 6/21/06133
SHOWER ENCLOSURES2 daysMon 6/12/06Tue 6/13/06114
APPLIANCES18 daysFri 5/26/06Tue 6/20/06 
Fireplaces1 dayFri 5/26/06Fri 5/26/06109
Hood1 dayFri 6/2/06Fri 6/2/06123
Appliances1 dayTue 6/20/06Tue 6/20/06102
FINAL CLEAN2 daysFri 6/23/06Mon 6/26/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysThu 10/6/05Fri 10/7/0510
Final Lift1 dayMon 5/1/06Mon 5/1/06 
LANDSCAPING5 daysMon 5/1/06Fri 5/5/06 
INSPECTIONS205 daysMon 9/12/05Fri 6/23/06 
Foundation1 dayMon 9/12/05Mon 9/12/0514
Underfloor1 dayThu 11/17/05Thu 11/17/0595
Framing & Shear1 dayMon 4/24/06Mon 4/24/0628
Ice Dam1 dayWed 4/12/06Wed 4/12/0678
Roof Nailing1 dayMon 4/10/06Mon 4/10/0626
ROUGH5 daysFri 4/28/06Thu 5/4/06 
A Unit1 dayFri 4/28/06Fri 4/28/0648
B Unit1 dayThu 5/4/06Thu 5/4/06101
INSULATION5 daysWed 5/3/06Tue 5/9/06 
A Unit1 dayWed 5/3/06Wed 5/3/0652
B Unit1 dayTue 5/9/06Tue 5/9/06105
DRYWALL8 daysMon 5/8/06Wed 5/17/06 
A Unit1 dayMon 5/8/06Mon 5/8/0655
B Unit1 dayWed 5/17/06Wed 5/17/06108
SHOWER PAN1 dayThu 5/18/06Thu 5/18/06111
FINAL 1 dayFri 6/23/06Fri 6/23/06118