« back to Old Greenwood - The Villas project page
« back to current projects
Isbell Construction Project Plan
A33 UNIT - The Villas at Old Greenwood
| Start Date: |
Thu 8/25/05 |
| Finish Date: |
Mon 6/26/06 |
| Name | Duration | Start Date | Finish Date | Predecessors |
| A 33 | 218 days | Wed 8/24/05 | Fri 6/23/06 | |
| EXCAVATION | 31 days | Wed 8/24/05 | Wed 10/5/05 | |
| Clear & Grub | 2 days | Wed 8/24/05 | Thu 8/25/05 | |
| Build Pad | 3 days | Fri 8/26/05 | Tue 8/30/05 | 3 |
| Dig Footings | 1 day | Wed 8/31/05 | Wed 8/31/05 | 4 |
| Stub Utilities | 1 day | Thu 9/1/05 | Thu 9/1/05 | 5 |
| Backfill | 2 days | Fri 9/16/05 | Mon 9/19/05 | 16 |
| Dig Piers & Slab Prep | 1 day | Wed 9/21/05 | Wed 9/21/05 | 17 |
| Install Utilities | 2 days | Fri 9/30/05 | Mon 10/3/05 | |
| Driveway & Final Grade | 2 days | Tue 10/4/05 | Wed 10/5/05 | 9 |
| FOUNDATION | 17 days | Wed 8/31/05 | Thu 9/22/05 | |
| Layout Footings | 1 day | Wed 8/31/05 | Wed 8/31/05 | 4 |
| Form Foundation | 5 days | Fri 9/2/05 | Thu 9/8/05 | 6 |
| Set Hardware | 1 day | Fri 9/9/05 | Fri 9/9/05 | 13 |
| Pour Foundation | 1 day | Tue 9/13/05 | Tue 9/13/05 | 140 |
| Strip Forms | 2 days | Wed 9/14/05 | Thu 9/15/05 | 15 |
| Layout Piers | 1 day | Tue 9/20/05 | Tue 9/20/05 | 7 |
| Pour Slabs and Piers | 1 day | Thu 9/22/05 | Thu 9/22/05 | 8 |
| FRAMING | 157 days | Mon 10/31/05 | Tue 6/6/06 | |
| Subfloor | 5 days | Mon 10/31/05 | Fri 11/4/05 | |
| Sheet Floor | 2 days | Mon 11/21/05 | Tue 11/22/05 | 51 |
| First Floor Walls | 8 days | Wed 1/25/06 | Fri 2/3/06 | |
| Second Floor | 7 days | Mon 2/6/06 | Tue 2/14/06 | 22 |
| Second Floor Walls | 18 days | Wed 2/15/06 | Fri 3/10/06 | 23 |
| Roof Framing | 15 days | Mon 3/13/06 | Fri 3/31/06 | 24 |
| Sheet Roof | 5 days | Mon 4/3/06 | Fri 4/7/06 | 25 |
| Interior Frame & Shear | 5 days | Mon 4/10/06 | Fri 4/14/06 | 26 |
| Framing Pick-up | 5 days | Mon 4/17/06 | Fri 4/21/06 | 27 |
| Tyvek | 4 days | Mon 4/3/06 | Thu 4/6/06 | 25 |
| Windows | 5 days | Fri 4/7/06 | Thu 4/13/06 | 29 |
| Exterior Doors | 2 days | Fri 4/14/06 | Mon 4/17/06 | 30 |
| Siding | 25 days | Tue 4/18/06 | Mon 5/22/06 | 31 |
| Decks | 6 days | Tue 5/23/06 | Tue 5/30/06 | 32 |
| Exterior Pick-up | 5 days | Wed 5/31/06 | Tue 6/6/06 | 33 |
| EXTERIOR STAIN | 5 days | Wed 6/7/06 | Tue 6/13/06 | 34 |
| A UNIT | 157 days | Thu 11/17/05 | Fri 6/23/06 | |
| PLUMBING | 152 days | Mon 11/7/05 | Tue 6/6/06 | |
| Under Floor | 3 days | Mon 11/7/05 | Wed 11/9/05 | 20 |
| Top Out | 5 days | Mon 4/10/06 | Fri 4/14/06 | 26 |
| Finish | 4 days | Thu 6/1/06 | Tue 6/6/06 | 61 |
| HVAC | 148 days | Thu 11/10/05 | Mon 6/5/06 | |
| Under Floor | 2 days | Thu 11/10/05 | Fri 11/11/05 | 38 |
| Top Out | 3 days | Mon 4/17/06 | Wed 4/19/06 | 39 |
| Set Equipment | 1 day | Mon 5/22/06 | Mon 5/22/06 | 63 |
| Finish | 1 day | Mon 6/5/06 | Mon 6/5/06 | 75 |
| ELECTRICAL | 83 days | Mon 2/6/06 | Wed 5/31/06 | |
| Set Panel | 1 day | Mon 2/6/06 | Mon 2/6/06 | 22 |
| Rough In | 6 days | Thu 4/20/06 | Thu 4/27/06 | 43 |
| Finish | 4 days | Fri 5/26/06 | Wed 5/31/06 | 67 |
| INSULATION | 118 days | Fri 11/18/05 | Tue 5/2/06 | |
| Under Floor | 1 day | Fri 11/18/05 | Fri 11/18/05 | 141 |
| Walls & Roof | 2 days | Mon 5/1/06 | Tue 5/2/06 | 146 |
| DRYWALL | 12 days | Mon 5/1/06 | Tue 5/16/06 | |
| Stock | 1 day | Mon 5/1/06 | Mon 5/1/06 | 146 |
| Hang | 4 days | Tue 5/2/06 | Fri 5/5/06 | 54 |
| Tape & Texture | 6 days | Tue 5/9/06 | Tue 5/16/06 | 152 |
| TILE | 18 days | Mon 5/8/06 | Wed 5/31/06 | |
| Shower Pans | 1 day | Mon 5/8/06 | Mon 5/8/06 | 55 |
| Showers | 5 days | Mon 5/22/06 | Fri 5/26/06 | 63 |
| Slabs | 4 days | Wed 5/24/06 | Mon 5/29/06 | 70 |
| Floors | 3 days | Mon 5/29/06 | Wed 5/31/06 | 59 |
| PAINTING | 14 days | Wed 5/17/06 | Mon 6/5/06 | |
| Interior Walls | 3 days | Wed 5/17/06 | Fri 5/19/06 | 56 |
| Putty & Caulk | 3 days | Thu 6/8/06 | Mon 6/12/06 | 73 |
| Final Touch Up | 1 day | Mon 6/5/06 | Mon 6/5/06 | 75 |
| FINISH CARPENTRY | 13 days | Mon 5/22/06 | Wed 6/7/06 | |
| Ceilings | 2 days | Wed 5/24/06 | Thu 5/25/06 | 70 |
| Doors & Casing | 2 days | Fri 5/26/06 | Mon 5/29/06 | 67 |
| Window Trim | 2 days | Tue 5/30/06 | Wed 5/31/06 | 68 |
| Cabinets | 2 days | Mon 5/22/06 | Tue 5/23/06 | 63 |
| Stair Rails | 1 day | Thu 6/1/06 | Thu 6/1/06 | 69 |
| Baseboard | 2 days | Mon 6/5/06 | Tue 6/6/06 | 74 |
| Closets & Pick Up | 1 day | Wed 6/7/06 | Wed 6/7/06 | 72 |
| HARDWOOD FLOORS | 2 days | Thu 6/1/06 | Fri 6/2/06 | 69 |
| CARPET | 1 day | Fri 6/2/06 | Fri 6/2/06 | 88 |
| SHOWER ENCLOSURES | 2 days | Thu 6/1/06 | Fri 6/2/06 | 61 |
| ROOFING | 20 days | Tue 4/11/06 | Mon 5/8/06 | |
| Dry In | 1 day | Tue 4/11/06 | Tue 4/11/06 | 144 |
| Flashings | 2 days | Mon 4/24/06 | Tue 4/25/06 | 28 |
| Roof | 18 days | Thu 4/13/06 | Mon 5/8/06 | 143 |
| MASONRY | 30 days | Wed 4/26/06 | Tue 6/6/06 | |
| Interior | 4 days | Mon 5/22/06 | Thu 5/25/06 | 63 |
| Exterior | 30 days | Wed 4/26/06 | Tue 6/6/06 | 79 |
| OVERHEAD DOORS | 1 day | Wed 6/7/06 | Wed 6/7/06 | 34 |
| APPLIANCES | 16 days | Wed 5/17/06 | Wed 6/7/06 | |
| Fireplace | 1 day | Wed 5/17/06 | Wed 5/17/06 | 56 |
| Hood | 1 day | Wed 5/24/06 | Wed 5/24/06 | 70 |
| Appliances | 1 day | Thu 6/1/06 | Thu 6/1/06 | 49 |
| B UNIT | 162 days | Thu 11/10/05 | Fri 6/23/06 | |
| PLUMBING | 158 days | Thu 11/10/05 | Mon 6/19/06 | |
| Underfloor | 3 days | Thu 11/10/05 | Mon 11/14/05 | 38 |
| Top Out | 5 days | Mon 4/17/06 | Fri 4/21/06 | 39 |
| Finish | 4 days | Wed 6/14/06 | Mon 6/19/06 | 127 |
| HVAC | 144 days | Fri 11/25/05 | Wed 6/14/06 | |
| Under Floor | 2 days | Tue 11/15/05 | Wed 11/16/05 | 91 |
| Top Out | 2 days | Mon 4/24/06 | Tue 4/25/06 | 92 |
| Set Equipment | 1 day | Wed 5/31/06 | Wed 5/31/06 | 116 |
| Finish | 1 day | Wed 6/14/06 | Wed 6/14/06 | 127 |
| ELECTRICAL | 96 days | Mon 2/6/06 | Mon 6/19/06 | |
| Set Panel | 1 day | Mon 2/6/06 | Mon 2/6/06 | 22 |
| Rough In | 6 days | Wed 4/26/06 | Wed 5/3/06 | 96 |
| Finish | 4 days | Wed 6/14/06 | Mon 6/19/06 | 127 |
| INSULATION | 122 days | Fri 11/18/05 | Mon 5/8/06 | |
| Under Floor | 1 day | Fri 11/18/05 | Fri 11/18/05 | 141 |
| Walls & Roof | 2 days | Fri 5/5/06 | Mon 5/8/06 | 147 |
| DRYWALL | 12 days | Wed 5/10/06 | Thu 5/25/06 | |
| Stock | 1 day | Wed 5/10/06 | Wed 5/10/06 | 150 |
| Hang | 4 days | Thu 5/11/06 | Tue 5/16/06 | 107 |
| Tape & Texture | 6 days | Thu 5/18/06 | Thu 5/25/06 | 153 |
| TILE | 18 days | Wed 5/17/06 | Fri 6/9/06 | |
| Shower Pans | 1 day | Wed 5/17/06 | Wed 5/17/06 | 108 |
| Showers | 5 days | Wed 5/31/06 | Tue 6/6/06 | 116 |
| Slabs | 4 days | Fri 6/2/06 | Wed 6/7/06 | 123 |
| Floors | 3 days | Wed 6/7/06 | Fri 6/9/06 | 112 |
| PAINTING | 20 days | Fri 5/26/06 | Thu 6/22/06 | |
| Interior Walls | 3 days | Fri 5/26/06 | Tue 5/30/06 | 109 |
| Putty & Caulk | 3 days | Mon 6/19/06 | Wed 6/21/06 | 126 |
| Final Touch Up | 1 day | Thu 6/22/06 | Thu 6/22/06 | 128 |
| FINISH CARPENTRY | 13 days | Wed 5/31/06 | Fri 6/16/06 | |
| Ceilings | 2 days | Fri 6/2/06 | Mon 6/5/06 | 123 |
| Doors & Casing | 2 days | Tue 6/6/06 | Wed 6/7/06 | 120 |
| Window Trim | 2 days | Thu 6/8/06 | Fri 6/9/06 | 121 |
| Cabinets | 2 days | Wed 5/31/06 | Thu 6/1/06 | 116 |
| Stair Rails | 1 day | Mon 6/12/06 | Mon 6/12/06 | 122 |
| Baseboard | 2 days | Wed 6/14/06 | Thu 6/15/06 | 127 |
| Closets & Pick Up | 1 day | Fri 6/16/06 | Fri 6/16/06 | 125 |
| HARDWOOD FLOORS | 2 days | Mon 6/12/06 | Tue 6/13/06 | 122 |
| CARPET | 1 day | Wed 6/21/06 | Wed 6/21/06 | 133 |
| SHOWER ENCLOSURES | 2 days | Mon 6/12/06 | Tue 6/13/06 | 114 |
| APPLIANCES | 18 days | Fri 5/26/06 | Tue 6/20/06 | |
| Fireplaces | 1 day | Fri 5/26/06 | Fri 5/26/06 | 109 |
| Hood | 1 day | Fri 6/2/06 | Fri 6/2/06 | 123 |
| Appliances | 1 day | Tue 6/20/06 | Tue 6/20/06 | 102 |
| FINAL CLEAN | 2 days | Fri 6/23/06 | Mon 6/26/06 | 118 |
| PAVING | 164 days | Wed 9/14/05 | Mon 5/1/06 | |
| Base & First Lift | 2 days | Thu 10/6/05 | Fri 10/7/05 | 10 |
| Final Lift | 1 day | Mon 5/1/06 | Mon 5/1/06 | |
| LANDSCAPING | 5 days | Mon 5/1/06 | Fri 5/5/06 | |
| INSPECTIONS | 205 days | Mon 9/12/05 | Fri 6/23/06 | |
| Foundation | 1 day | Mon 9/12/05 | Mon 9/12/05 | 14 |
| Underfloor | 1 day | Thu 11/17/05 | Thu 11/17/05 | 95 |
| Framing & Shear | 1 day | Mon 4/24/06 | Mon 4/24/06 | 28 |
| Ice Dam | 1 day | Wed 4/12/06 | Wed 4/12/06 | 78 |
| Roof Nailing | 1 day | Mon 4/10/06 | Mon 4/10/06 | 26 |
| ROUGH | 5 days | Fri 4/28/06 | Thu 5/4/06 | |
| A Unit | 1 day | Fri 4/28/06 | Fri 4/28/06 | 48 |
| B Unit | 1 day | Thu 5/4/06 | Thu 5/4/06 | 101 |
| INSULATION | 5 days | Wed 5/3/06 | Tue 5/9/06 | |
| A Unit | 1 day | Wed 5/3/06 | Wed 5/3/06 | 52 |
| B Unit | 1 day | Tue 5/9/06 | Tue 5/9/06 | 105 |
| DRYWALL | 8 days | Mon 5/8/06 | Wed 5/17/06 | |
| A Unit | 1 day | Mon 5/8/06 | Mon 5/8/06 | 55 |
| B Unit | 1 day | Wed 5/17/06 | Wed 5/17/06 | 108 |
| SHOWER PAN | 1 day | Thu 5/18/06 | Thu 5/18/06 | 111 |
| FINAL | 1 day | Fri 6/23/06 | Fri 6/23/06 | 118 |
|