NameDurationStart DateFinish DatePredecessors
A 34235 daysThu 8/18/05Wed 7/12/06 
EXCAVATION35 daysThu 8/18/05Wed 10/5/05 
Clear & Grub2 daysThu 8/18/05Fri 8/19/05 
Build Pad3 daysMon 8/22/05Wed 8/24/053
Dig Footings1 dayThu 8/25/05Thu 8/25/054
Stub Utilities1 dayFri 8/26/05Fri 8/26/055
Backfill2 daysTue 9/13/05Wed 9/14/0516
Dig Piers & Slab Prep1 dayFri 9/16/05Fri 9/16/0517
Install Utilities3 daysWed 9/28/05Fri 9/30/05 
Driveway & Final Grade3 daysMon 10/3/05Wed 10/5/059
FOUNDATION18 daysThu 8/25/05Mon 9/19/05 
Layout Footings1 dayThu 8/25/05Thu 8/25/054
Form Foundation6 daysMon 8/29/05Mon 9/5/056
Set Hardware1 dayTue 9/6/05Tue 9/6/0513
Pour Foundation1 dayThu 9/8/05Thu 9/8/05185
Strip Forms2 daysFri 9/9/05Mon 9/12/0515
Layout Piers1 dayThu 9/15/05Thu 9/15/057
Pour Slabs and Piers1 dayMon 9/19/05Mon 9/19/058
FRAMING177 daysMon 10/24/05Tue 6/27/06 
Subfloor6 daysMon 10/24/05Mon 10/31/05 
Sheet Floor3 daysTue 11/15/05Thu 11/17/0551
First Floor Walls11 daysWed 1/11/06Wed 1/25/06 
Second Floor8 daysThu 1/26/06Mon 2/6/0622
Second Floor Walls24 daysTue 2/7/06Fri 3/10/0623
Roof Framing20 daysMon 3/13/06Fri 4/7/0624
Sheet Roof7 daysMon 4/10/06Tue 4/18/0625
Interior Frame & Shear5 daysWed 4/19/06Tue 4/25/0626
Framing Pick-up5 daysWed 4/26/06Tue 5/2/0627
Tyvek5 daysMon 4/10/06Fri 4/14/0625
Windows6 daysMon 4/17/06Mon 4/24/0629
Exterior Doors3 daysTue 4/25/06Thu 4/27/0630
Siding30 daysFri 4/28/06Thu 6/8/0631
Decks8 daysFri 6/9/06Tue 6/20/0632
Exterior Pick-up5 daysWed 6/21/06Tue 6/27/0633
EXTERIOR STAIN5 daysWed 6/28/06Tue 7/4/0634
A UNIT203 daysMon 10/3/05Wed 7/12/06 
PLUMBING166 daysTue 11/1/05Tue 6/20/06 
Under Floor3 daysTue 11/1/05Thu 11/3/0520
Top Out5 daysWed 4/19/06Tue 4/25/0626
Finish4 daysThu 6/15/06Tue 6/20/0661
HVAC165 daysFri 11/4/05Thu 6/22/06 
Under Floor2 daysFri 11/4/05Mon 11/7/0538
Top Out3 daysWed 4/26/06Fri 4/28/0639
Set Equipment1 dayWed 5/31/06Wed 5/31/0663
Finish1 dayThu 6/22/06Thu 6/22/0675
ELECTRICAL103 daysThu 1/26/06Mon 6/19/06 
Set Panel1 dayThu 1/26/06Thu 1/26/0622
Rough In6 daysMon 5/1/06Mon 5/8/0643
Finish4 daysWed 6/14/06Mon 6/19/0674
INSULATION129 daysMon 11/14/05Thu 5/11/06 
Under Floor1 dayMon 11/14/05Mon 11/14/05186
Walls & Roof2 daysWed 5/10/06Thu 5/11/06191
DRYWALL12 daysWed 5/10/06Thu 5/25/06 
Stock1 dayWed 5/10/06Wed 5/10/06191
Hang4 daysThu 5/11/06Tue 5/16/0654
Tape & Texture6 daysThu 5/18/06Thu 5/25/06199
TILE21 daysWed 5/17/06Wed 6/14/06 
Shower Pans1 dayWed 5/17/06Wed 5/17/0655
Showers5 daysWed 5/31/06Tue 6/6/0663
Slabs4 daysFri 6/2/06Wed 6/7/0670
Floors3 daysMon 6/12/06Wed 6/14/0669
PAINTING20 daysFri 5/26/06Thu 6/22/06 
Interior Walls3 daysFri 5/26/06Tue 5/30/0656
Putty & Caulk3 daysMon 6/19/06Wed 6/21/0673
Final Touch Up1 dayThu 6/22/06Thu 6/22/0675
FINISH CARPENTRY13 daysWed 5/31/06Fri 6/16/06 
Ceilings2 daysFri 6/2/06Mon 6/5/0670
Doors & Casing2 daysTue 6/6/06Wed 6/7/0667
Window Trim2 daysThu 6/8/06Fri 6/9/0668
Cabinets2 daysWed 5/31/06Thu 6/1/0663
Stair Rails 1 dayMon 6/12/06Mon 6/12/0669
Baseboard2 daysWed 6/14/06Thu 6/15/0674
Closets & Pick Up1 dayFri 6/16/06Fri 6/16/0672
HARDWOOD FLOORS2 daysMon 6/12/06Tue 6/13/0669
CARPET1 dayWed 6/21/06Wed 6/21/0688
SHOWER ENCLOSURES2 daysThu 6/15/06Fri 6/16/0661
ROOFING20 daysThu 4/20/06Wed 5/17/06 
Dry In1 dayThu 4/20/06Thu 4/20/06189
Flashings2 daysWed 5/3/06Thu 5/4/0628
Roof18 daysMon 4/24/06Wed 5/17/06188
MASONRY35 daysFri 1/20/06Thu 3/9/06 
Interior6 daysWed 5/31/06Wed 6/7/0663
Exterior35 daysFri 1/20/06Thu 3/9/06 
OVERHEAD DOORS1 dayWed 6/28/06Wed 6/28/0634
APPLIANCES18 daysFri 5/26/06Tue 6/20/06 
Fireplace1 dayFri 5/26/06Fri 5/26/0656
Hood1 dayFri 6/2/06Fri 6/2/0670
Appliances1 dayTue 6/20/06Tue 6/20/0649
B UNIT179 daysFri 11/4/05Wed 7/12/06 
PLUMBING165 daysFri 11/4/05Thu 6/22/06 
Underfloor3 daysFri 11/4/05Tue 11/8/0538
Top Out5 daysWed 4/26/06Tue 5/2/0639
Finish4 daysMon 6/19/06Thu 6/22/06127
HVAC159 daysWed 11/9/05Mon 6/19/06 
Under Floor2 daysWed 11/9/05Thu 11/10/0591
Top Out3 daysWed 5/3/06Fri 5/5/0692
Set Equipment1 dayMon 6/5/06Mon 6/5/06116
Finish1 dayMon 6/19/06Mon 6/19/06127
ELECTRICAL105 daysThu 1/26/06Wed 6/21/06 
Set Panel1 dayThu 1/26/06Thu 1/26/0622
Rough In5 daysMon 5/8/06Fri 5/12/0696
Finish3 daysMon 6/19/06Wed 6/21/06127
INSULATION133 daysMon 11/14/05Wed 5/17/06 
Under Floor1 dayMon 11/14/05Mon 11/14/05186
Walls & Roof2 daysTue 5/16/06Wed 5/17/06192
DRYWALL8 daysFri 5/19/06Tue 5/30/06 
Stock1 dayFri 5/19/06Fri 5/19/06196
Hang2 daysMon 5/22/06Tue 5/23/06107
Tape & Texture4 daysThu 5/25/06Tue 5/30/06200
TILE14 daysWed 5/24/06Mon 6/12/06 
Shower Pans1 dayWed 5/24/06Wed 5/24/06108
Showers4 daysMon 6/5/06Thu 6/8/06116
Slabs3 daysWed 6/7/06Fri 6/9/06123
Floors2 daysFri 6/9/06Mon 6/12/06112
PAINTING19 daysWed 5/31/06Mon 6/26/06 
Interior Walls3 daysWed 5/31/06Fri 6/2/06109
Putty & Caulk3 daysMon 6/19/06Wed 6/21/06127
Final Touch Up1 dayMon 6/26/06Mon 6/26/06128
FINISH CARPENTRY13 daysMon 6/5/06Wed 6/21/06 
Ceilings2 daysWed 6/7/06Thu 6/8/06123
Doors & Casing2 daysFri 6/9/06Mon 6/12/06120
Window Trim2 daysTue 6/13/06Wed 6/14/06121
Cabinets2 daysMon 6/5/06Tue 6/6/06116
Stair Rails1 dayThu 6/15/06Thu 6/15/06122
Baseboard2 daysMon 6/19/06Tue 6/20/06127
Closets & Pick Up1 dayWed 6/21/06Wed 6/21/06125
HARDWOOD FLOORS2 daysThu 6/15/06Fri 6/16/06122
CARPET1 dayFri 6/23/06Fri 6/23/06133
SHOWER ENCLOSURES2 daysTue 6/13/06Wed 6/14/06114
APPLIANCES17 daysWed 5/31/06Thu 6/22/06 
Fireplaces1 dayWed 5/31/06Wed 5/31/06109
Hood1 dayWed 6/7/06Wed 6/7/06123
Appliances1 dayThu 6/22/06Thu 6/22/06102
C UNIT178 daysMon 11/7/05Wed 7/12/06 
PLUMBING196 daysThu 10/6/05Thu 7/6/06 
Underfloor3 daysThu 10/6/05Mon 10/10/05 
Top Out5 daysWed 5/3/06Tue 5/9/0692
Finish4 daysMon 7/3/06Thu 7/6/06172
HVAC190 daysTue 10/11/05Mon 7/3/06 
Under Floor2 daysTue 10/11/05Wed 10/12/05136
Top Out3 daysWed 5/10/06Fri 5/12/06137
Set Equipment1 dayMon 6/19/06Mon 6/19/06161
Finish1 dayMon 7/3/06Mon 7/3/06172
ELECTRICAL179 daysMon 10/31/05Thu 7/6/06 
Set Panel1 dayMon 10/31/05Mon 10/31/05 
Rough In6 daysMon 5/15/06Mon 5/22/06141
Finish4 daysMon 7/3/06Thu 7/6/06172
INSULATION139 daysMon 11/14/05Thu 5/25/06 
Under Floor1 dayMon 11/14/05Mon 11/14/05186
Walls & Roof2 daysWed 5/24/06Thu 5/25/06193
DRYWALL12 daysMon 5/29/06Tue 6/13/06 
Stock1 dayMon 5/29/06Mon 5/29/06197
Hang4 daysTue 5/30/06Fri 6/2/06152
Tape & Texture6 daysTue 6/6/06Tue 6/13/06201
TILE18 daysMon 6/5/06Wed 6/28/06 
Shower Pans1 dayMon 6/5/06Mon 6/5/06153
Showers5 daysMon 6/19/06Fri 6/23/06161
Slabs4 daysWed 6/21/06Mon 6/26/06168
Floors3 daysMon 6/26/06Wed 6/28/06157
PAINTING20 daysWed 6/14/06Tue 7/11/06 
Interior Walls3 daysWed 6/14/06Fri 6/16/06154
Putty & Caulk3 daysMon 7/3/06Wed 7/5/06172
Final Touch Up1 dayTue 7/11/06Tue 7/11/06173
FINISH CARPENTRY13 daysMon 6/19/06Wed 7/5/06 
Ceilings2 daysWed 6/21/06Thu 6/22/06168
Doors & Casing2 daysFri 6/23/06Mon 6/26/06165
Window Trim2 daysTue 6/27/06Wed 6/28/06166
Cabinets2 daysMon 6/19/06Tue 6/20/06161
Stair Rails1 dayThu 6/29/06Thu 6/29/06167
Baseboard2 daysMon 7/3/06Tue 7/4/06172
Closets & Pick Up1 dayWed 7/5/06Wed 7/5/06170
HARDWOOD FLOORS2 daysThu 6/29/06Fri 6/30/06167
CARPET1 dayMon 7/10/06Mon 7/10/06178
SHOWER ENCLOSURES2 daysThu 6/29/06Fri 6/30/06159
APPLIANCES18 daysWed 6/14/06Fri 7/7/06 
Fireplaces1 dayWed 6/14/06Wed 6/14/06154
Hood1 dayWed 6/21/06Wed 6/21/06168
Appliances1 dayFri 7/7/06Fri 7/7/06147
FINAL CLEAN2 daysTue 6/27/06Wed 6/28/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysThu 10/6/05Fri 10/7/0510
Final Lift1 dayMon 5/15/06Mon 5/15/06 
LANDSCAPING5 daysThu 6/1/06Wed 6/7/06 
INSPECTIONS221 daysWed 9/7/05Wed 7/12/06 
Foundation1 dayWed 9/7/05Wed 9/7/0514
Underfloor1 dayFri 11/11/05Fri 11/11/0595
Framing & Shear1 dayWed 5/3/06Wed 5/3/0628
Ice Dam1 dayFri 4/21/06Fri 4/21/0678
Roof Nailing1 dayWed 4/19/06Wed 4/19/0626
ROUGH11 daysTue 5/9/06Tue 5/23/06 
A Unit1 dayTue 5/9/06Tue 5/9/0648
B Unit1 dayMon 5/15/06Mon 5/15/06101
C Unit1 dayTue 5/23/06Tue 5/23/06146
INSULATION11 daysFri 5/12/06Fri 5/26/06 
A Unit1 dayFri 5/12/06Fri 5/12/0652
B Unit1 dayThu 5/18/06Thu 5/18/06105
C Unit1 dayFri 5/26/06Fri 5/26/06150
DRYWALL14 daysWed 5/17/06Mon 6/5/06 
A Unit1 dayWed 5/17/06Wed 5/17/0655
B Unit1 dayWed 5/24/06Wed 5/24/06108
C Unit1 dayMon 6/5/06Mon 6/5/06153
SHOWER PAN14 daysThu 5/18/06Tue 6/6/06 
A Unit1 dayThu 5/18/06Thu 5/18/0658
B Unit1 dayThu 5/25/06Thu 5/25/06111
C Unit1 dayTue 6/6/06Tue 6/6/06156
FINAL 1 dayWed 7/12/06Wed 7/12/06163