Isbell Construction Project Plan

A36 UNIT - The Villas at Old Greenwood



Start Date: Thu 8/25/05
Finish Date: Fri 5/5/06

NameDurationStart DateFinish DatePredecessors
A 36191 daysMon 8/8/05Mon 5/1/06 
EXCAVATION32 daysMon 8/8/05Tue 9/20/05 
Clear & Grub2 daysMon 8/8/05Tue 8/9/05 
Build Pad3 daysWed 8/10/05Fri 8/12/053
Dig Footings1 dayMon 8/15/05Mon 8/15/054
Stub Utilities1 dayTue 8/16/05Tue 8/16/055
Backfill2 daysWed 8/31/05Thu 9/1/0516
Dig Piers & Slab Prep1 dayMon 9/5/05Mon 9/5/0517
Install Utilities2 daysWed 9/21/05Thu 9/22/05 
Driveway & Final Grade2 daysFri 9/23/05Mon 9/26/059
FOUNDATION20 daysWed 8/10/05Tue 9/6/05 
Layout Footings1 dayWed 8/10/05Wed 8/10/053
Form Foundation5 daysWed 8/17/05Tue 8/23/056
Set Hardware1 dayWed 8/24/05Wed 8/24/0513
Pour Foundation1 dayFri 8/26/05Fri 8/26/05140
Strip Forms2 daysMon 8/29/05Tue 8/30/0515
Layout Piers1 dayFri 9/2/05Fri 9/2/057
Pour Slabs and Piers1 dayTue 9/6/05Tue 9/6/058
FRAMING132 daysMon 10/10/05Tue 4/11/06 
Subfloor5 daysMon 10/10/05Fri 10/14/05 
Sheet Floor2 daysMon 10/31/05Tue 11/1/0551
First Floor Walls8 daysWed 11/30/05Fri 12/9/05 
Second Floor7 daysMon 12/12/05Tue 12/20/0522
Second Floor Walls18 daysWed 12/21/05Fri 1/13/0623
Roof Framing15 daysMon 1/16/06Fri 2/3/0624
Sheet Roof5 daysMon 2/6/06Fri 2/10/0625
Interior Frame & Shear5 daysMon 2/13/06Fri 2/17/0626
Framing Pick-up5 daysMon 2/20/06Fri 2/24/0627
Tyvek4 daysMon 2/6/06Thu 2/9/0625
Windows5 daysFri 2/10/06Thu 2/16/0629
Exterior Doors2 daysFri 2/17/06Mon 2/20/0630
Siding25 daysTue 2/21/06Mon 3/27/0631
Decks6 daysTue 3/28/06Tue 4/4/0632
Exterior Pick-up5 daysWed 4/5/06Tue 4/11/0633
EXTERIOR STAIN5 daysWed 4/12/06Tue 4/18/0634
A UNIT141 daysMon 10/17/05Mon 5/1/06 
PLUMBING127 daysMon 10/17/05Tue 4/11/06 
Under Floor3 daysMon 10/17/05Wed 10/19/0520
Top Out5 daysMon 2/13/06Fri 2/17/0626
Finish4 daysThu 4/6/06Tue 4/11/0661
HVAC127 daysThu 10/20/05Fri 4/14/06 
Under Floor2 daysThu 10/20/05Fri 10/21/0538
Top Out3 daysMon 2/20/06Wed 2/22/0639
Set Equipment1 dayMon 3/27/06Mon 3/27/0663
Finish1 dayMon 4/10/06Mon 4/10/0675
ELECTRICAL83 daysMon 12/12/05Wed 4/5/06 
Set Panel1 dayMon 12/12/05Mon 12/12/0522
Rough In6 daysThu 2/23/06Thu 3/2/0643
Finish4 daysFri 3/31/06Wed 4/5/0667
INSULATION93 daysFri 10/28/05Tue 3/7/06 
Under Floor1 dayFri 10/28/05Fri 10/28/05141
Walls & Roof2 daysMon 3/6/06Tue 3/7/06146
DRYWALL12 daysMon 3/6/06Tue 3/21/06 
Stock1 dayMon 3/6/06Mon 3/6/06146
Hang4 daysTue 3/7/06Fri 3/10/0654
Tape & Texture6 daysTue 3/14/06Tue 3/21/06152
TILE18 daysMon 3/13/06Wed 4/5/06 
Shower Pans1 dayMon 3/13/06Mon 3/13/0655
Showers5 daysMon 3/27/06Fri 3/31/0663
Slabs4 daysWed 3/29/06Mon 4/3/0670
Floors3 daysMon 4/3/06Wed 4/5/0659
PAINTING18 daysWed 3/22/06Fri 4/14/06 
Interior Walls3 daysWed 3/22/06Fri 3/24/0656
Putty & Caulk3 daysThu 4/13/06Mon 4/17/0673
Final Touch Up1 dayMon 4/10/06Mon 4/10/0675
FINISH CARPENTRY13 daysMon 3/27/06Wed 4/12/06 
Ceilings2 daysWed 3/29/06Thu 3/30/0670
Doors & Casing2 daysFri 3/31/06Mon 4/3/0667
Window Trim2 daysTue 4/4/06Wed 4/5/0668
Cabinets2 daysMon 3/27/06Tue 3/28/0663
Stair Rails 1 dayThu 4/6/06Thu 4/6/0669
Baseboard2 daysMon 4/10/06Tue 4/11/0674
Closets & Pick Up1 dayWed 4/12/06Wed 4/12/0672
HARDWOOD FLOORS2 daysThu 4/6/06Fri 4/7/0669
CARPET1 dayFri 4/7/06Fri 4/7/0688
SHOWER ENCLOSURES2 daysThu 4/6/06Fri 4/7/0661
ROOFING20 daysTue 2/14/06Mon 3/13/06 
Dry In1 dayTue 2/14/06Tue 2/14/06144
Flashings2 daysMon 2/27/06Tue 2/28/0628
Roof18 daysThu 2/16/06Mon 3/13/06143
MASONRY30 daysWed 3/1/06Tue 4/11/06 
Interior4 daysMon 3/27/06Thu 3/30/0663
Exterior30 daysWed 3/1/06Tue 4/11/0679
OVERHEAD DOORS1 dayWed 4/12/06Wed 4/12/0634
APPLIANCES16 daysWed 3/22/06Wed 4/12/06 
Fireplace1 dayWed 3/22/06Wed 3/22/0656
Hood1 dayWed 3/29/06Wed 3/29/0670
Appliances1 dayThu 4/6/06Thu 4/6/0649
B UNIT138 daysThu 10/20/05Mon 5/1/06 
PLUMBING134 daysThu 10/20/05Tue 4/25/06 
Underfloor3 daysThu 10/20/05Mon 10/24/0538
Top Out5 daysMon 2/20/06Fri 2/24/0639
Finish4 daysThu 4/20/06Tue 4/25/06127
HVAC128 daysTue 10/25/05Thu 4/20/06 
Under Floor2 daysTue 10/25/05Wed 10/26/0591
Top Out3 daysMon 2/27/06Wed 3/1/0692
Set Equipment1 dayThu 4/6/06Thu 4/6/06116
Finish1 dayThu 4/20/06Thu 4/20/06127
ELECTRICAL97 daysMon 12/12/05Tue 4/25/06 
Set Panel1 dayMon 12/12/05Mon 12/12/0522
Rough In6 daysThu 3/2/06Thu 3/9/0696
Finish4 daysThu 4/20/06Tue 4/25/06127
INSULATION98 daysFri 10/28/05Tue 3/14/06 
Under Floor1 dayFri 10/28/05Fri 10/28/05141
Walls & Roof2 daysMon 3/13/06Tue 3/14/06147
DRYWALL12 daysThu 3/16/06Fri 3/31/06 
Stock1 dayThu 3/16/06Thu 3/16/06150
Hang4 daysFri 3/17/06Wed 3/22/06107
Tape & Texture6 daysFri 3/24/06Fri 3/31/06153
TILE18 daysThu 3/23/06Mon 4/17/06 
Shower Pans1 dayThu 3/23/06Thu 3/23/06108
Showers5 daysThu 4/6/06Wed 4/12/06116
Slabs4 daysMon 4/10/06Thu 4/13/06123
Floors3 daysThu 4/13/06Mon 4/17/06112
PAINTING18 daysMon 4/3/06Wed 4/26/06 
Interior Walls3 daysMon 4/3/06Wed 4/5/06109
Putty & Caulk3 daysThu 4/20/06Mon 4/24/06127
Final Touch Up1 dayFri 4/28/06Fri 4/28/06128
FINISH CARPENTRY13 daysThu 4/6/06Mon 4/24/06 
Ceilings2 daysMon 4/10/06Tue 4/11/06123
Doors & Casing2 daysWed 4/12/06Thu 4/13/06120
Window Trim2 daysFri 4/14/06Mon 4/17/06121
Cabinets2 daysThu 4/6/06Fri 4/7/06116
Stair Rails1 dayTue 4/18/06Tue 4/18/06122
Baseboard2 daysThu 4/20/06Fri 4/21/06127
Closets & Pick Up1 dayMon 4/24/06Mon 4/24/06125
HARDWOOD FLOORS2 daysTue 4/18/06Wed 4/19/06122
CARPET1 dayThu 4/27/06Thu 4/27/06133
SHOWER ENCLOSURES2 daysTue 4/18/06Wed 4/19/06114
APPLIANCES18 daysMon 4/3/06Wed 4/26/06 
Fireplaces1 dayMon 4/3/06Mon 4/3/06109
Hood1 dayMon 4/10/06Mon 4/10/06123
Appliances1 dayWed 4/26/06Wed 4/26/06102
FINAL CLEAN2 daysMon 5/1/06Tue 5/2/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysTue 9/27/05Wed 9/28/0510
Final Lift1 dayMon 5/1/06Mon 5/1/06 
LANDSCAPING5 daysMon 5/1/06Fri 5/5/06 
INSPECTIONS178 daysThu 8/25/05Mon 5/1/06 
Foundation1 dayThu 8/25/05Thu 8/25/0514
Underfloor1 dayThu 10/27/05Thu 10/27/0595
Framing & Shear1 dayMon 2/27/06Mon 2/27/0628
Ice Dam1 dayWed 2/15/06Wed 2/15/0678
Roof Nailing1 dayMon 2/13/06Mon 2/13/0626
ROUGH6 daysFri 1/20/06Fri 1/27/06 
A Unit1 dayFri 3/3/06Fri 3/3/0648
B Unit1 dayFri 3/10/06Fri 3/10/06101
INSULATION6 daysWed 1/25/06Wed 2/1/06 
A Unit1 dayWed 3/8/06Wed 3/8/0652
B Unit1 dayWed 3/15/06Wed 3/15/06105
DRYWALL9 daysMon 1/30/06Thu 2/9/06 
A Unit1 dayMon 3/13/06Mon 3/13/0655
B Unit1 dayThu 3/23/06Thu 3/23/06108
SHOWER PAN1 dayFri 3/24/06Fri 3/24/06111
FINAL 1 dayMon 5/1/06Mon 5/1/06118