Isbell Construction Project Plan

A37 UNIT - The Villas at Old Greenwood



Start Date: Thu 8/25/05
Finish Date: Fri 5/5/06

NameDurationStart DateFinish DatePredecessors
A 37 179 daysWed 8/3/05Mon 4/10/06 
EXCAVATION32 daysWed 8/3/05Thu 9/15/05 
Clear & Grub2 daysWed 8/3/05Thu 8/4/05 
Build Pad3 daysFri 8/5/05Tue 8/9/053
Dig Footings1 dayWed 8/10/05Wed 8/10/054
Stub Utilities1 dayThu 8/11/05Thu 8/11/055
Backfill2 daysFri 8/26/05Mon 8/29/0516
Dig Piers & Slab Prep1 dayWed 8/31/05Wed 8/31/0517
Install Utilities2 daysFri 9/16/05Mon 9/19/05 
Driveway & Final Grade2 daysTue 9/20/05Wed 9/21/059
FOUNDATION17 daysWed 8/10/05Thu 9/1/05 
Layout Footings1 dayWed 8/10/05Wed 8/10/054
Form Foundation5 daysFri 8/12/05Thu 8/18/056
Set Hardware1 dayFri 8/19/05Fri 8/19/0513
Pour Foundation1 dayTue 8/23/05Tue 8/23/05140
Strip Forms2 daysWed 8/24/05Thu 8/25/0515
Layout Piers1 dayTue 8/30/05Tue 8/30/057
Pour Slabs and Piers1 dayThu 9/1/05Thu 9/1/058
FRAMING122 daysMon 10/3/05Tue 3/21/06 
Subfloor5 daysMon 10/3/05Fri 10/7/05 
Sheet Floor2 daysMon 10/24/05Tue 10/25/0551
First Floor Walls8 daysWed 11/9/05Fri 11/18/05 
Second Floor7 daysMon 11/21/05Tue 11/29/0522
Second Floor Walls18 daysWed 11/30/05Fri 12/23/0523
Roof Framing15 daysMon 12/26/05Fri 1/13/0624
Sheet Roof5 daysMon 1/16/06Fri 1/20/0625
Interior Frame & Shear5 daysMon 1/23/06Fri 1/27/0626
Framing Pick-up5 daysMon 1/30/06Fri 2/3/0627
Tyvek4 daysMon 1/16/06Thu 1/19/0625
Windows5 daysFri 1/20/06Thu 1/26/0629
Exterior Doors2 daysFri 1/27/06Mon 1/30/0630
Siding25 daysTue 1/31/06Mon 3/6/0631
Decks6 daysTue 3/7/06Tue 3/14/0632
Exterior Pick-up5 daysWed 3/15/06Tue 3/21/0633
EXTERIOR STAIN5 daysWed 3/22/06Tue 3/28/0634
A UNIT131 daysMon 10/10/05Mon 4/10/06 
PLUMBING117 daysMon 10/10/05Tue 3/21/06 
Under Floor3 daysMon 10/10/05Wed 10/12/0520
Top Out5 daysMon 1/23/06Fri 1/27/0626
Finish4 daysThu 3/16/06Tue 3/21/0661
HVAC117 daysThu 10/13/05Fri 3/24/06 
Under Floor2 daysThu 10/13/05Fri 10/14/0538
Top Out3 daysMon 1/30/06Wed 2/1/0639
Set Equipment1 dayMon 3/6/06Mon 3/6/0663
Finish1 dayFri 3/24/06Fri 3/24/0675
ELECTRICAL83 daysMon 11/21/05Wed 3/15/06 
Set Panel1 dayMon 11/21/05Mon 11/21/0522
Rough In6 daysThu 2/2/06Thu 2/9/0643
Finish4 daysFri 3/10/06Wed 3/15/0667
INSULATION83 daysFri 10/21/05Tue 2/14/06 
Under Floor1 dayFri 10/21/05Fri 10/21/05141
Walls & Roof2 daysMon 2/13/06Tue 2/14/06146
DRYWALL12 daysMon 2/13/06Tue 2/28/06 
Stock1 dayMon 2/13/06Mon 2/13/06146
Hang4 daysTue 2/14/06Fri 2/17/0654
Tape & Texture6 daysTue 2/21/06Tue 2/28/06152
TILE18 daysMon 2/20/06Wed 3/15/06 
Shower Pans18 daysMon 2/20/06Wed 3/15/0655
Showers5 daysMon 3/6/06Fri 3/10/0663
Slabs4 daysWed 3/8/06Mon 3/13/0670
Floors3 daysMon 3/13/06Wed 3/15/0659
PAINTING18 daysWed 3/1/06Fri 3/24/06 
Interior Walls3 daysWed 3/1/06Fri 3/3/0656
Putty & Caulk3 daysThu 3/23/06Mon 3/27/0673
Final Touch Up1 dayFri 3/24/06Fri 3/24/0675
FINISH CARPENTRY13 daysMon 3/6/06Wed 3/22/06 
Ceilings2 daysWed 3/8/06Thu 3/9/0670
Doors & Casing2 daysFri 3/10/06Mon 3/13/0667
Window Trim2 daysTue 3/14/06Wed 3/15/0668
Cabinets2 daysMon 3/6/06Tue 3/7/0663
Stair Rails 1 dayThu 3/16/06Thu 3/16/0669
Baseboard2 daysMon 3/20/06Tue 3/21/0674
Closets & Pick Up1 dayWed 3/22/06Wed 3/22/0672
HARDWOOD FLOORS2 daysThu 3/16/06Fri 3/17/0669
CARPET1 dayThu 3/23/06Thu 3/23/0685
SHOWER ENCLOSURES2 daysThu 3/16/06Fri 3/17/0661
ROOFING20 daysTue 1/24/06Mon 2/20/06 
Dry In1 dayTue 1/24/06Tue 1/24/06144
Flashings2 daysMon 2/6/06Tue 2/7/0628
Roof18 daysThu 1/26/06Mon 2/20/06143
MASONRY30 daysWed 2/8/06Tue 3/21/06 
Interior4 daysMon 3/6/06Thu 3/9/0663
Exterior30 daysWed 2/8/06Tue 3/21/0679
OVERHEAD DOORS1 dayWed 3/22/06Wed 3/22/0634
APPLIANCES16 daysWed 3/1/06Wed 3/22/06 
Fireplace1 dayWed 3/1/06Wed 3/1/0656
Hood1 dayWed 3/8/06Wed 3/8/0670
Appliances1 dayThu 3/16/06Thu 3/16/0649
B UNIT128 daysThu 10/13/05Mon 4/10/06 
PLUMBING122 daysThu 10/13/05Fri 3/31/06 
Underfloor3 daysThu 10/13/05Mon 10/17/0538
Top Out5 daysMon 1/30/06Fri 2/3/0639
Finish4 daysThu 3/30/06Tue 4/4/06127
HVAC118 daysTue 10/18/05Thu 3/30/06 
Under Floor2 daysTue 10/18/05Wed 10/19/0591
Top Out3 daysMon 2/6/06Wed 2/8/0692
Set Equipment1 dayThu 3/16/06Thu 3/16/06116
Finish1 dayThu 3/30/06Thu 3/30/06127
ELECTRICAL95 daysMon 11/21/05Fri 3/31/06 
Set Panel1 dayMon 11/21/05Mon 11/21/0522
Rough In6 daysThu 2/9/06Thu 2/16/0696
Finish4 daysThu 3/30/06Tue 4/4/06127
INSULATION88 daysFri 10/21/05Tue 2/21/06 
Under Floor1 dayFri 10/21/05Fri 10/21/05141
Walls & Roof2 daysMon 2/20/06Tue 2/21/06147
DRYWALL12 daysThu 2/23/06Fri 3/10/06 
Stock1 dayThu 2/23/06Thu 2/23/06150
Hang4 daysFri 2/24/06Wed 3/1/06107
Tape & Texture6 daysFri 3/3/06Fri 3/10/06153
TILE18 daysThu 3/2/06Mon 3/27/06 
Shower Pans1 dayThu 3/2/06Thu 3/2/06108
Showers5 daysThu 3/16/06Wed 3/22/06116
Slabs4 daysMon 3/20/06Thu 3/23/06123
Floors3 daysThu 3/23/06Mon 3/27/06112
PAINTING20 daysMon 3/13/06Fri 4/7/06 
Interior Walls3 daysMon 3/13/06Wed 3/15/06109
Putty & Caulk3 daysThu 3/30/06Mon 4/3/06127
Final Touch Up1 dayFri 4/7/06Fri 4/7/06128
FINISH CARPENTRY13 daysThu 3/16/06Mon 4/3/06 
Ceilings2 daysMon 3/20/06Tue 3/21/06123
Doors & Casing2 daysWed 3/22/06Thu 3/23/06120
Window Trim2 daysFri 3/24/06Mon 3/27/06121
Cabinets2 daysThu 3/16/06Fri 3/17/06116
Stair Rails1 dayTue 3/28/06Tue 3/28/06122
Baseboard2 daysThu 3/30/06Fri 3/31/06127
Closets & Pick Up1 dayMon 4/3/06Mon 4/3/06125
HARDWOOD FLOORS2 daysTue 3/28/06Wed 3/29/06122
CARPET1 dayThu 4/6/06Thu 4/6/06133
SHOWER ENCLOSURES2 daysTue 3/28/06Wed 3/29/06114
APPLIANCES18 daysMon 3/13/06Wed 4/5/06 
Fireplaces1 dayMon 3/13/06Mon 3/13/06109
Hood1 dayMon 3/20/06Mon 3/20/06123
Appliances1 dayWed 4/5/06Wed 4/5/06102
FINAL CLEAN2 daysMon 4/10/06Tue 4/11/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysThu 9/22/05Fri 9/23/0510
Final Lift1 dayMon 5/1/06Mon 5/1/06 
LANDSCAPING5 daysMon 5/1/06Fri 5/5/06 
INSPECTIONS166 daysMon 8/22/05Mon 4/10/06 
Foundation1 dayMon 8/22/05Mon 8/22/0514
Underfloor1 dayThu 10/20/05Thu 10/20/0595
Framing & Shear1 dayMon 2/6/06Mon 2/6/0628
Ice Dam1 dayWed 1/25/06Wed 1/25/0678
Roof Nailing1 dayMon 1/23/06Mon 1/23/0626
ROUGH6 daysFri 2/10/06Fri 2/17/06 
A Unit1 dayFri 2/10/06Fri 2/10/0648
B Unit1 dayFri 2/17/06Fri 2/17/06101
INSULATION6 daysWed 2/15/06Wed 2/22/06 
A Unit1 dayWed 2/15/06Wed 2/15/0652
B Unit1 dayWed 2/22/06Wed 2/22/06105
DRYWALL9 daysMon 2/20/06Thu 3/2/06 
A Unit1 dayMon 2/20/06Mon 2/20/0655
B Unit1 dayThu 3/2/06Thu 3/2/06108
SHOWER PAN1 dayFri 3/3/06Fri 3/3/06111
FINAL 1 dayMon 4/10/06Mon 4/10/06118