Isbell Construction Project Plan

A38 UNIT - The Villas at Old Greenwood



Start Date: Sun 8/14/05
Finish Date: Fri 5/5/06

NameDurationStart_DateFinish_DatePredecessors
A 38 166 daysMon 8/1/05Mon 3/20/06 
EXCAVATION32 daysMon 8/1/05Tue 9/13/05 
Clear & Grub2 daysMon 8/1/05Tue 8/2/05 
Build Pad3 daysWed 8/3/05Fri 8/5/053
Dig Footings1 dayMon 8/8/05Mon 8/8/054
Stub Utilities1 dayTue 8/9/05Tue 8/9/055
Backfill2 daysMon 8/22/05Tue 8/23/0516
Dig Piers & Slab Prep1 dayThu 8/25/05Thu 8/25/0517
Install Utilities2 daysTue 9/13/05Wed 9/14/05 
Driveway & Final Grade2 daysThu 9/15/05Fri 9/16/059
FOUNDATION15 daysMon 8/8/05Fri 8/26/05 
Layout Footings1 dayMon 8/8/05Mon 8/8/054
Form Foundation5 daysWed 8/10/05Tue 8/16/056
Set Hardware1 dayWed 8/17/05Wed 8/17/0513
Pour Foundation1 dayWed 8/17/05Wed 8/17/05140
Strip Forms2 daysThu 8/18/05Fri 8/19/0515
Layout Piers1 dayWed 8/24/05Wed 8/24/057
Pour Slabs and Piers1 dayFri 8/26/05Fri 8/26/058
FRAMING112 daysMon 9/26/05Tue 2/28/06 
Subfloor5 daysMon 9/26/05Fri 9/30/05 
Sheet Floor2 daysMon 10/17/05Tue 10/18/0551
First Floor Walls8 daysWed 10/19/05Fri 10/28/0521
Second Floor7 daysMon 10/31/05Tue 11/8/0522
Second Floor Walls18 daysWed 11/9/05Fri 12/2/0523
Roof Framing15 daysMon 12/5/05Fri 12/23/0524
Sheet Roof5 daysMon 12/26/05Fri 12/30/0525
Interior Frame & Shear5 daysMon 1/2/06Fri 1/6/0626
Framing Pick-up5 daysMon 1/9/06Fri 1/13/0627
Tyvek4 daysMon 12/26/05Thu 12/29/0525
Windows5 daysFri 12/30/05Thu 1/5/0629
Exterior Doors2 daysFri 1/6/06Mon 1/9/0630
Siding25 daysTue 1/10/06Mon 2/13/0631
Decks6 daysTue 2/14/06Tue 2/21/0632
Exterior Pick-up5 daysWed 2/22/06Tue 2/28/0633
EXTERIOR STAIN5 daysWed 3/1/06Tue 3/7/0634
A UNIT121 daysMon 10/3/05Mon 3/20/06 
PLUMBING107 daysMon 10/3/05Tue 2/28/06 
Under Floor3 daysMon 10/3/05Wed 10/5/0520
Top Out5 daysMon 1/2/06Fri 1/6/0626
Finish4 daysThu 2/23/06Tue 2/28/0661
HVAC117 daysThu 10/6/05Fri 3/17/06 
Under Floor2 daysThu 10/6/05Fri 10/7/0538
Top Out3 daysMon 1/9/06Wed 1/11/0639
Set Equipment1 dayMon 2/13/06Mon 2/13/0663
Finish1 dayMon 2/27/06Mon 2/27/0675
ELECTRICAL83 daysMon 10/31/05Wed 2/22/06 
Set Panel1 dayMon 10/31/05Mon 10/31/0522
Rough In6 daysThu 1/12/06Thu 1/19/0643
Finish4 daysFri 2/17/06Wed 2/22/0667
INSULATION73 daysFri 10/14/05Tue 1/24/06 
Under Floor1 dayFri 10/14/05Fri 10/14/05141
Walls & Roof2 daysMon 1/23/06Tue 1/24/06146
DRYWALL12 daysMon 1/23/06Tue 2/7/06 
Stock1 dayMon 1/23/06Mon 1/23/06146
Hang4 daysTue 1/24/06Fri 1/27/0654
Tape & Texture6 daysTue 1/31/06Tue 2/7/06152
TILE18 daysMon 1/30/06Wed 2/22/06 
Shower Pans1 dayMon 1/30/06Mon 1/30/0655
Showers5 daysMon 2/13/06Fri 2/17/0663
Slabs4 daysWed 2/15/06Mon 2/20/0670
Floors3 daysMon 2/20/06Wed 2/22/0659
PAINTING18 daysWed 2/8/06Fri 3/3/06 
Interior Walls3 daysWed 2/8/06Fri 2/10/0656
Putty & Caulk3 daysThu 3/2/06Mon 3/6/0673
Final Touch Up1 dayMon 2/27/06Mon 2/27/0675
FINISH CARPENTRY13 daysMon 2/13/06Wed 3/1/06 
Ceilings2 daysWed 2/15/06Thu 2/16/0670
Doors & Casing2 daysFri 2/17/06Mon 2/20/0667
Window Trim2 daysTue 2/21/06Wed 2/22/0668
Cabinets2 daysMon 2/13/06Tue 2/14/0663
Stair Rails 1 dayThu 2/23/06Thu 2/23/0669
Baseboard2 daysMon 2/27/06Tue 2/28/0674
Closets & Pick Up1 dayWed 3/1/06Wed 3/1/0672
HARDWOOD FLOORS2 daysThu 2/23/06Fri 2/24/0669
CARPET1 dayFri 2/24/06Fri 2/24/0688
SHOWER ENCLOSURES2 daysThu 2/23/06Fri 2/24/0661
ROOFING20 daysTue 1/3/06Mon 1/30/06 
Dry In1 dayTue 1/3/06Tue 1/3/06144
Flashings2 daysMon 1/16/06Tue 1/17/0628
Roof18 daysThu 1/5/06Mon 1/30/06143
MASONRY30 daysFri 1/20/06Thu 3/2/06 
Interior4 daysMon 2/13/06Thu 2/16/0663
Exterior30 daysFri 1/20/06Thu 3/2/0679
OVERHEAD DOORS1 dayWed 3/1/06Wed 3/1/0634
APPLIANCES16 daysWed 2/8/06Wed 3/1/06 
Fireplace1 dayWed 2/8/06Wed 2/8/0656
Hood1 dayWed 2/15/06Wed 2/15/0670
Appliances1 dayThu 2/23/06Thu 2/23/0649
B UNIT118 daysThu 10/6/05Mon 3/20/06 
PLUMBING114 daysThu 10/6/05Tue 3/14/06 
Underfloor3 daysThu 10/6/05Mon 10/10/0538
Top Out5 daysMon 1/9/06Fri 1/13/0639
Finish4 daysThu 3/9/06Tue 3/14/06127
HVAC108 daysTue 10/11/05Thu 3/9/06 
Under Floor2 daysTue 10/11/05Wed 10/12/0591
Top Out3 daysMon 1/16/06Wed 1/18/0692
Set Equipment1 dayThu 2/23/06Thu 2/23/06116
Finish1 dayThu 3/9/06Thu 3/9/06127
ELECTRICAL97 daysMon 10/31/05Tue 3/14/06 
Set Panel1 dayMon 10/31/05Mon 10/31/0522
Rough In6 daysThu 1/19/06Thu 1/26/0696
Finish4 daysThu 3/9/06Tue 3/14/06127
INSULATION78 daysFri 10/14/05Tue 1/31/06 
Under Floor1 dayFri 10/14/05Fri 10/14/05141
Walls & Roof2 daysMon 1/30/06Tue 1/31/06147
DRYWALL12 daysThu 2/2/06Fri 2/17/06 
Stock1 dayThu 2/2/06Thu 2/2/06150
Hang4 daysFri 2/3/06Wed 2/8/06107
Tape & Texture6 daysFri 2/10/06Fri 2/17/06153
TILE18 daysThu 2/9/06Mon 3/6/06 
Shower Pans1 dayThu 2/9/06Thu 2/9/06108
Showers5 daysThu 2/23/06Wed 3/1/06116
Slabs4 daysMon 2/27/06Thu 3/2/06123
Floors3 daysThu 3/2/06Mon 3/6/06112
PAINTING20 daysMon 2/20/06Fri 3/17/06 
Interior Walls3 daysMon 2/20/06Wed 2/22/06109
Putty & Caulk3 daysThu 3/9/06Mon 3/13/06127
Final Touch Up1 dayFri 3/17/06Fri 3/17/06128
FINISH CARPENTRY13 daysThu 2/23/06Mon 3/13/06 
Ceilings2 daysMon 2/27/06Tue 2/28/06123
Doors & Casing2 daysWed 3/1/06Thu 3/2/06120
Window Trim2 daysFri 3/3/06Mon 3/6/06121
Cabinets2 daysThu 2/23/06Fri 2/24/06116
Stair Rails1 dayTue 3/7/06Tue 3/7/06122
Baseboard2 daysThu 3/9/06Fri 3/10/06127
Closets & Pick Up1 dayMon 3/13/06Mon 3/13/06125
HARDWOOD FLOORS2 daysTue 3/7/06Wed 3/8/06121
CARPET1 dayThu 3/16/06Thu 3/16/06133
SHOWER ENCLOSURES2 daysTue 3/7/06Wed 3/8/06114
APPLIANCES18 daysMon 2/20/06Wed 3/15/06 
Fireplaces1 dayMon 2/20/06Mon 2/20/06109
Hood1 dayMon 2/27/06Mon 2/27/06123
Appliances1 dayWed 3/15/06Wed 3/15/06102
FINAL CLEAN2 daysMon 3/20/06Tue 3/21/06118
PAVING164 daysWed 9/14/05Mon 5/1/06 
Base & First Lift2 daysMon 9/19/05Tue 9/20/0510
Final Lift1 dayMon 5/1/06Mon 5/1/06 
LANDSCAPING5 daysMon 5/1/06Fri 5/5/06 
INSPECTIONS155 daysTue 8/16/05Mon 3/20/06 
Foundation1 dayTue 8/16/05Tue 8/16/05 
Underfloor1 dayThu 10/13/05Thu 10/13/0595
Framing & Shear1 dayMon 1/16/06Mon 1/16/0628
Ice Dam1 dayWed 1/4/06Wed 1/4/0678
Roof Nailing1 dayMon 1/2/06Mon 1/2/0626
ROUGH6 daysFri 1/20/06Fri 1/27/06 
A Unit1 dayFri 1/20/06Fri 1/20/0648
B Unit1 dayFri 1/27/06Fri 1/27/06101
INSULATION6 daysWed 1/25/06Wed 2/1/06 
A Unit1 dayWed 1/25/06Wed 1/25/0652
B Unit1 dayWed 2/1/06Wed 2/1/06105
DRYWALL9 daysMon 1/30/06Thu 2/9/06 
A Unit1 dayMon 1/30/06Mon 1/30/0655
B Unit1 dayThu 2/9/06Thu 2/9/06108
SHOWER PAN1 dayFri 2/10/06Fri 2/10/06111
FINAL 1 dayMon 3/20/06Mon 3/20/06118